Springbank Dam – Installation Highlights

CEC completed key installation work for the Springbank Dam project, including:

  • 8,401.52 m² CC70 Cable Concrete (ACB)

  • 9,979.84 m² of non-woven geotextile

  • 2000 m³ of 3B placement

  • 161.85 m³ of granular base course (Zone 4A)

  • Geogrid installation

Working with Vinci, CEC delivered these installations in difficult access conditions, using cranes, loaders, and large excavators to place CC70 and other materials safely and efficiently. Despite the challenging terrain, our team completed the work on schedule and to project specifications..